beautypg.com

Chapter 3: installation – Sterling GP Series User Manual

Page 13

background image

GP Series Portable Chillers

Chapter 3: Installation

13 of 44

Chapter 3: Installation

3-1 Uncrating

All models are are shipped mounted on a skid, enclosed in a plastic wrapper, and open-crated
on all four sides and top.

1. Pry the crating away from the skid.
2. Use a pry bar to remove the blocks securing the unit to the skid.
3. Lift unit from sides, inserting forklift under the base. The forks must be equidistant

from the centerline of the unit and the unit must be balanced on the forks. Lift slowly
and only high enough to clear the skid. Use a pry bar if necessary to carefully remove
the skid from the unit.

4. Lower slowly. The unit should land on its casters or rails and can then be moved into

position.

5. Retain the crating material for reshipping the chiller in case hidden shipping damage

is found.

3-2 Electrical

Connections

Supply electricity of the voltage, phase, and cycle listed on the serial tag. Total running amps
are also found in the specification tables on pages in the Appendix.

Bring properly sized power leads and ground from a fused disconnect (installed by your
electrician) to the unit. Use dual-element fuses in the disconnect switch, sized according to
the National Electrical Code recommendations. Note the outline drawings for egress into the
cabinet. Make sure all electrical connections are tight.

Important!

Refer to your local electrical requirements for proper feeder conductor and

supply disconnecting sizing. For instance, in the United States refer to

National Electric Code (NEC) Article 430-24 through 430-26, Table

310.15(B)(2)(a)