P R E P A R A T I O N

In addition to the reservoirs, we also recommend
that you lubricate all other points on the
machine at this time. This can be accomplished
by following the maintenance schedule on
Page 64.

Note:

If this lathe was shipped with oil in the

reservoirs, do not change that oil until after the
test run and spindle break-in procedures.

Adding Coolant

Add the coolant of your choice now. For detailed
instructions on where the coolant tank is located
and how to add fluid, refer to Coolant System
Service
on Page 71.

Power Connection

Once your machine is set up and assembled as
previously described in this manual, it is ready to
be connected to the power source.

Note About Extension Cords:

Using an

incorrectly sized extension cord may decrease the
life of electrical components on your machine.
Refer to Extension Cords on Page 18 for more
information.

To connect the power cord to the lathe:

1.

Make sure the master power switch is

turned to the OFF position, then open the
electrical cabinet door.

2.

Thread the power cord through the strain

relief, and up to the master power switch
shown in Figure 20.

Electrocution or fire
may occur if machine is
ungrounded, incorrectly
connected to power, or
connected to an undersized
circuit. Use an electrician or
a qualified service personnel
to ensure a safe power
connection.

Figure 20. Location to connect power inside main

electrical cabinet.

Incoming

Power

Strain

Relief

Master

Power

Switch

3.

Connect the incoming hot wires to the

upper master power switch terminals, as
illustrated in Figure 21.

4.

Connect the incoming ground wire to the

ground terminal on the switch bracket, as
illustrated in Figure 21.

Ground

Hot

Hot

To Plug

Figure 21. Power connection at master power switch.

Master

Power

Switch