A2.0 installation procedure – MTS Criterion 40 - Installation and Commissioning Plan User Manual

Page 7

background image

Installation and Commissioning Plan


MTS Criterion

TM

Series 40

7

A2.0 INSTALLATION

PROCEDURE

The system will be installed by an FSE. Depending on the system configuration,

the following activities will be performed:

Item Description

Performed

On Site

A2.1

Verify that all components purchased are present

according to the purchase contract and packing list.

A2.2

Attach all required cables between the controller and

load unit.

-

Transducers

-

Computer

A2.3

Install purchased grips and fixtures as required

(including any auxiliary power supplies for grips).

A2.4

Install purchased environmental simulation products.

(For example, any furnaces, chambers, and baths.)