MTS Criterion 40 - Installation and Commissioning Plan User Manual

Page 3

background image

Installation and Commissioning Plan


MTS Criterion

TM

Series 40

3

This Installation and Commissioning Plan is a part of MTS system service, and is

included in the price of the system. The tasks outlined in sections A and B are

expected to be completed in two days. The customer is responsible for

completing tasks A1.1 through A1.5 before the MTS FSE or MTS Authorized

Service Representative (referred to as FSE throughout this document) arrives on

site.

The purpose of the Installation and Commissioning Plan is to ensure that the

supplied system and accessories function correctly. Following completion of the

Installation Procedure, sections A2.1 through A3.3, the FSE will provide an on-

site introduction to system operation, sections A4.1 through B2.6.

A1.0 CUSTOMER FACILITIES AND CUSTOMER RESPONSIBILITIES

Note: After your order confirmation, you will receive a “Site preparation Guide”

to help you comply with the requirements in this section.

The requirements in the following subsections, A1.1 through A1.5, are the

responsibility of the customer and should be completed before the arrival of the

FSE.

A1.1 Suitable equipment and personnel to unload and set in place all items in the contract

should be available for system installation.

A1.2 Suitable electrical power for MTS supplied equipment should be provided. This

electrical supply should be clean and free from power transients caused by other

equipment on the circuit.

Series 40: 200-240 V AC (Load frame power), 110-240 V AC (PC power), 50-60 Hz

single phase.

A1.3 The electronic components and computer equipment should be located in a suitable

environment with respect to temperature, humidity, and dust.

A1.4 The equipment operator should be proficient in the use and navigation of a personnel

computer, including such tasks as booting the system, file management, printing, and the

use of spreadsheet applications such as Microsoft

®

Excel.

A1.5 Before the visit, the FSE will contact you to confirm the following information:

Type of testing. Do you run any known standards such as ASTM, ISO, or