SMA BEAM REPEATER User Manual
Page 11

SMA Solar Technology AG
Determining the Installation Location
User Manual
SBeamRep-BEN091911
11
12. Return to the "SETUP/SERVICE/DIAGNOSTICS" menu.
13. You can now walk away with the Sunny Beam towards the desired installation location until the
communication quality is still at least 50 %.
14. If you have reached the desired installation location with sufficient communication quality,
commissioning is successfully completed at this point.
Set the data request frequency back to a value of at least 15 seconds or higher via the menu
"VIEW OPTIONS/DATA REQUEST FREQ.".
15. If you cannot yet reach the desired installation location with sufficient communication quality,
change the installation location of the Sunny Beam Repeater. Even altering the position by only
a few meters may improve the communication quality.
16. After successful commissioning, set the data request frequency back to a value of at least 15
seconds or higher via the menu "VIEW OPTIONS/DATA REQUEST FREQ.".