13 Decommissioning the Inverter

To decommission the inverter completely upon completion of its service life, proceed as described
in this Section. If the inverter is defective and you have received a replacement device, observe the
information on how to proceed when receiving a replacement device (see Section 12 "Procedure
for Receiving a Replacement Device", page 37)
.

Risk of injury when lifting the inverter, or if it is dropped
The inverter weighs 61 kg. There is risk of injury if the inverter is lifted incorrectly or dropped while
being transported or when attaching it to or removing it from the wall mounting bracket.

• Carry and lift the inverter in an upright position

with several people without tilting it. With one
hand grasp the recessed grip, and with the
other hand support the top part of the
enclosure. This will prevent the inverter tipping
forward.

• If the inverter is to be transported and lifted

with a crane, remove the filler plugs on the top
of the inverter and screw the eye bolts into the
threads.

Procedure:

1.

Danger to life due to high voltages

• Disconnect the inverter from all voltage sources (see Section 2.2, page 7).

2. Remove the AC cable from the inverter. Press the locking levers all the way upward and pull

the conductors out of the connecting terminal plate for the AC cable.

3. Press down the locking levers of the connecting terminal plate for the AC cable.
4. If the multi-function relay or the SMA Power Control Module are used, remove the connection

cable from the inverter.

5. If other cables (e.g. data cables or network cables) are connected, remove them from the

inverter.