10. Switch on the circuit breaker of all three line conductors.

☑ All three LEDs start to glow and the start-up phase begins. The start-up phase may take several

minutes.

☑ The green LED is glowing. Feed-in operation begins.

✖ The green LED is flashing?

Possible cause of error: the DC input voltage is still too low or the inverter is monitoring the
utility grid.

• Once the DC input voltage is sufficiently high and the grid connection conditions are met,

the inverter will start operation.

✖ The red LED is glowing and an error message and event number appear in the display?

Eliminate the error (see Section 5 "Troubleshooting", page 12).