34

Using Automation Assist mode

Delaying the next scheduled primary event’s playout

secondary items that have the same start time and then plays out the items. This results in a
short execution delay before the actual items replace what is currently playing out on air.

Note:

Operators should be aware that iTX does not wait for secondary items

that cannot be cued in time; nor does it cue the primary items following the
item being forced on air. As such, after an operator uses the iMC panel’s

Take

Next

button, they should use the iMC panel’s

Cue Next

button to manually

cue the next scheduled items and then check that all required items are cued
before performing a subsequent

Take Next

operation.

Delaying the next scheduled primary event’s playout

Since live source events often have unpredictable start and end times, operators must be
ready at any time to take the next scheduled item without delay. A powerful technique for
achieving this is to put the next scheduled item on hold using the iMC panel’s

Hold Next

button.

The

Hold Next

button temporarily suspends the item that follows the current on-air items

and continues to play the current on air items until a

Take Next

operation is executed.

There are two common scenarios for holding the next scheduled events:

Delaying the start of a live source event

, on page 34

Delaying the ending of a live source event

, on page 35

Delaying the start of a live source event

When the next scheduled item is a live source event, the live content may not be ready to
go on air at the scheduled time. For example, the scheduled coverage of a live press
conference is delayed. In such a case, the operator will keep playing the current on air item
until the press conference is ready to begin.

To accomplish this, the operator presses the iMC panel’s

Cue Next

and then

Hold Next

buttons to ready the next scheduled item (live source event), but prevent it from playing.
This puts a hold on the remaining items in the schedule until the live source event is ready.
When it is time to join the live source event, the operator simply presses the iMC panel’s

Take Next

button and the iTX automation system resumes control of running the schedule

by playing out the subsequent events.

Figure 4-1

on page 34 demonstrates that the primary and secondary master control events

(IN-072 and N07) are cued, but placed on hold. The clip that is currently on air (BITC PAL SD)
keep playing and the schedule will keep bumping out until the operator executes a Take
Next operation.

Fig. 4-1: Delaying the start of the next live source event using the iMC’s Hold Next operation