INSTALLATION PROCEDURES

4

T-80 and T-85 . . .

Installation on Straight Run Piping

Tracers are to be run parallel and in direct contact with the
process pipe where possible. Tracer location on pipe is to be
where most accessible. If more than two tracers are used,
they should be equally spaced circumferentially around the
pipe.

1. Install tracers as shown below. Pressure test tracing for
leaks with steam pressure equal to or greater than the normal
operating pressure or preferably with suitable hydrostatic
tests. Repair any leaks and retest until the tracing system is
free of leaks.

Illustration D: Fillet Application

Illustration E: T-80 and T-85

Triple Tracer

Dual Tracer

Single Tracer

Insulation

Tracer

T-80 or T-85 Heat

Transfer Compound

12 mm x 0.5 mm

Stainless Steel

Banding and Seals

2. Attach tracer to process piping with stainless steel banding
and crimp seals in accordance with Illustration A (see T-3 and
T-99 installation).

3. Apply fillet of compound along sides of the tracer as shown
on Illustration D below.

4. Insulate and weatherproof equipment.

Note . . .
T-80 and T-85 are not soluble in water. However, systems employing T-80 or T-85 which

are not insulated should be temporarily protected from the erosive action of rain or mois-

ture during the curing period.

D

2D

Typical Cross Section

Process Pipe

Fillet of T-80 or T-85 Heat

Transfer Compound

Hand Gun

Tracer

75 mm

Minimum

45°

120°

120°

Note . . .
For ease of installation and serviceability, all tracers shall be installed parallel to and

against the heated pipe or equipment and shall be placed on the most accessible sur-

face location in regard to supports, ease of installation, connection and thermal insula-

tion. Multiple tracers shall be equally spaced around the circumference of the pipe.

45°

120°