Remko, Kps 300, Commissioning – REMKO KPS300 User Manual

Page 10

background image

10

REMKO

KPS 300

Heat pump supply line

5/4“ AG

Heat pump return line

5/4“ AG

Heating circuit supply
5/4“ AG

Heating circuit return line and
emptying through customer-
provided T-section 5/4" AG

Optional: Electric booster
heating (immersion
heating) 6/4" IG

Immersion tube

for temperature sensor

Cleaning flange or

opening for fin-tube

heat exchanger D180

(special accessory)

Top 1" AG connection,
for: venting, safety group

Variant 2: Heat pump located to the

left of the storage tank

Commissioning

1.

Check all connections, even those
which were sealed at the factory
(flange), for leak-tightness.

2 Then check all pipes for any leaks

and, if necessary, fix them.

Commissioning should only be

performed and documented by

specially trained personnel.

NOTE

3.

Test the safety module and valves
for function.

4. During the heating process, all

expansion water generated in
the tank must be captured by an
appropriate expansion vessel.