OnLine Power
6002-033
Rev
C
3-5
3-1-2
Output Power Cable Installation
CAUTION
Output power cable should be installed by a licensed electrical contractor or certified Facilities
Engineer in accordance with local codes.
DANGER!!
VERIFY THAT INCOMING HIGH VOLTAGE CIRCUITS ARE DE-ENERGIZED BEFORE
CONTINUING WITH THIS PROCEDURE.
1.
Turn facility circuit breaker to OFF, lock and tagout in accordance with OSHA Lockout/Tagout requirements.
2.
Remove front panel by unbolting six screws at corners and at left and right sides of each panel.
3.
Cut proper size hole in side panel to match output conduit.
4.
Insert cable/conduit through hole in panel and into hole in frame. Secure cable/conduit with appropriate fitting.
5.
Remove 3/4 inch of insulation from each conductor.
6.
Identify each conductor according to phase, neutral or ground.
7.
Connect conductors as follows:
a. Identify each phase conductor according to phase A, B, C (X1, X2, X3)
b. Route phase conductors to output lugs (see Illustrations 1-2 or 1-3. Also see Illustration 3-1, 3-2, or 3-3). Torque to
25 in-lb (29 NM).
c. Route neutral conductor to X0 lug. Torque to 25 in-lb (29 NM).
d. Route grounding conductor to ground lug.
e. Insert prepared end of grounding conductor into ground lug and torque to 25 in-lb (29 NM).