Receiving and Unpacking

1. Check packing slip to ensure ALL material has been delivered.
2. All material shortages are to be reported to Nortec within 48 hours from receipt of goods. Nortec

assumes no responsibility for any material shortages beyond this period.

3. Inspect shipping boxes for damage and note damages on shipping waybill accordingly.
4. After unpacking, inspect equipment for damage and if damage is found, notify the shipper

promptly.

5. All Nortec products are shipped on an FOB factory basis. Any and all damage, breakage or loss

claims are to be made directly to the shipping company.

Before Installation

1. Ensure that available voltage and phase corresponds with Blower Pack voltage and phase as

indicated on Blower Pack’s specification label.

2. Ensure that the dedicated external fuse disconnect is of sufficient size to handle the rated amps

as indicated on the specification label. Refer to local codes.

3. Report any discrepancy immediately to the site engineer.
4. Ensure sufficient clearances will be available as described in the “

Location and Mounting

section.

5. Ensure steam lines can be routed to blower pack as described in the “

Steam Lines

” section.

Figure 1. Specification Label Location RM-BP and NH-EL Space