9252000994 Rev P
BE1-50/51B-214/-215/-223/-225 Testing
5-1
SECTION 5 • TESTING
General
Dielectric testing, operational testing, and periodic testing are described in the following paragraphs.
Dielectric Test
In accordance with IEC 255-5 and IEEE C37.90-2005, one-minute dielectric (high potential) tests may be
performed as follows:
•
All circuits to ground: 2,828 Vdc or 2,000 Vac
•
Input to output circuits: 2,828 Vdc or 2,000 Vac
Output contacts are surge protected.
Operational Test Procedure
The following procedures verify operation of relays BE1-50/51B-214/-215/-223 (5 ampere model) and
BE1-50/51B-225 (1 ampere model). The test setup of Figures 5-1 and 5-2 (BE1-50/51B-214/-225) are
intended primarily as an illustration of the principles involved. The BE1-50/51B-215 is illustrated in Figures
5-3 and 5-4. The BE1-50/51B-223 is illustrated in Figures 5-5 and 5-6. Other test setups known to be
capable of testing with the stated and implied tolerances (including equipment specifically designed for
testing relays) may be used.
Test Equipment Required
•
Current source with a range from 0 to 20 Aac (sensing input current)
•
AC or DC voltage source (target operation)
•
Timer or counter
CAUTION
To ensure proper timing during testing, before each test, remove the current
from the unit for R times D seconds (refer to Section 1, Specifications, Time
Reset for R and D definitions).
Figure 5-1. Pickup and Timing Test Setup, BE1-50/51B-214/-225
BE1-50/51B-214/-225
6
5
3
1
TIME
INST
2
CURRENT
SOURCE
INPUT
STOP
TIMER
START
AMPS
TEST SET
P0059-08