Figure 4-1. coordination timing diagram – Basler Electric BE1-50/51B-121 User Manual
Page 38
![background image](https://www.manualsdir.com/files/773816/content/doc038.png)
4-2
BE1-50/51B-214/-215/-223/-225 Installation
9252000994 Rev P
From the reset characteristic curve equation.
1
M
RD
T
2
Reset
−
=
seconds
15.5
1
0
2
7.75
2
−
=
−
×
=
M = 0 if current goes to zero.
Negative result indicates reset time.
Results: Full trip = 0.209 seconds and full reset = 15.5 seconds if current goes to zero.
In Figure 4-1,
T
A
= 0.209 seconds (relay was at reset).
T
B
= value < T
A
because rewind has not gone to zero.
T
C
= value < T
A
because rewind has not gone to zero.
Figure 4-1. Coordination Timing Diagram
Equation for time to trip during rewind (before relay is reset).
(
)(
)
Rewind
Full
Time
Rewind
Trip
Full
T
Occurence
This
Trip
=
Second Operation
(
)( )
15.5
3
0.209
T
B
=
seconds
0.040
T
B
=
Third Operation
(
)(
)
15.5
11.96
0.209
T
C
=
seconds
0.161
T
C
=