4. Route the supply wires and the grounding wire through the hole on the back of the oven. Use a strain-
relief fitting.
5. Attach each supply wire to the appropriate terminal of the contactor or terminal block (according to the
wiring diagrams starting on page 30), taking care not to disconnect any wires that may already be
connected to the contactor or terminal block.
6. Insert the ground wire into the grounding lug and tighten the screw.
7. Check that all connections match the wiring diagram and are tight.
8. Reattach the right-side panel and insulation; and the lower-front panel.
Step 6: Check the Installation
1. Check that all screws and bolts are tightened.
2. Move the oven into the position at which it will be operated.
3. Check that the oven is level. If not, adjust the legs.
4. Check that the appropriate clearances are satisfied (see page 7).
5. Turn-on supply power and check oven for proper operation.