Controller, Table a. generator start connections, 4 --- settings – Winco ULPSS40/I WITH DSE 7310 ENGINE CONTROL (2014) User Manual
Page 12: 5 --- automatic generator exerciser, Clock battery, Exercise with or without load, Table b. generator exercise settings
1
4030-00
60706-50
Note: Any relay closure can be used to start and stop this
generator. As long as the contact stays closed the engine
generator set will continue to run. Once the relay is opened
the unit will shut down and remain in the standby mode until
the remote start relay is closed again.
B - ESTOP- & ESTOP+. Remote Emergency Stop terminals.
These two terminals are shipped with a jumper installed. If your
application requires the installation of a Remote Emergency
Stop switch, remove the jumper and wire your switch to these
terminals.
This unit will not start and run without either the
jumper installed or a remote N/C switch installed..
C - Battery Charger Failure. Battery charger failure relay input
from remote battery charger to DSE7310 controller.
D - Remote Display Panel Interface Terminals. These
interface terminals are prewired to allow for the connection of a
remote display. This display allows for the remote annunciation
of alarms at a location such as a nurses station or a control
room.
*******CAUTION******
Never run the AC and DC wiring in the same conduit.
NOTE: The right hand half of the customer connection
terminal block is for programmable inputs and outputs.
Although these terminals are wired into the DSE7310,
they are not normally programed. This terminal block has
connections for four programmable inputs and four putputs
along with one flex input and a ground. Consult the factory
at 507-357-6831 before attempting to program these inputs/
outputs.
DC Interconnections to the Automatic Transfer Switch
Two control wires are required between the A.T.S. panel and the
generator control terminal box. Depending on the distance, 14 to
16 gauge stranded wire should be used. These wires should be
labeled S1 and S3.
****************
***** WARNING *****
****************
Be sure Engine Generator is in the “OFF” position before you
make any DC interconnections.
ASCO 185 UL SWITCH
Your DC connection points in the ASCO 185 ATS are
terminals “4” and “5 on the interface terminal block. As this is a
“DRY” unpowered contract set it make no difference which lead
(battery negative #1 or start #23) connect to which terminal.
ASCO 300 UL SWITCH
Your DC connection points in the ASCO 300 ATS are terminals
“14” and “15”. Depending on the size of the switch they are
located in different locations. As this is a “DRY” unpowered
contact set it make no difference which lead (battery negative #1
or start #23) connect to which terminal.
CONTROLLER
Series 185
(continued)
3
381333–319 D
3 --- Generator Starting Contacts
The generator starting contacts connections are on the
controller. Refer to the generator manual. Disconnect
the generator battery and verify that the ignition switch is
in the OFF position. Connect the generator starting
wires to the appropriate terminals on terminal block TB7
as shown on the wiring diagram. For wiring convenience
terminal block TB7 has a removable plug. See Figure 4
and Table A.
TB7
removable
terminal block
TB7–4, TB7–5, TB7–6
1 2 3 4 5 6 7 8 9
Figure 4. TB7 generator starting contact terminals.
Table A. Generator Start Connections
When the Utility fails
Terminals on Controller
contact closes
TB7–4 and TB7–5
contact opens
TB7–5 and TB7–6
4 --- Settings
The time delay and sensor setting in the Group 4
controller are accessible on the inside. Refer to Tables B
and C and to Figures 6 and 7. Use a ball–point pen or
other pointed tool to slide the DIP switch actuators up or
down to match setting shown.
All power must be off before making any changes.
The factory default settings are shown in Table G on
page 5.
screw
cover must be removed
to replace 9V battery
(use alkaline type)
Figure 5. Battery replacement.
5 --- Automatic Generator Exerciser
The built–in automatic generator exerciser can be set to
exercise the generator for 20 minutes once every week.
Clock Battery
Be sure a fresh battery is installed and turned on. It will
maintain the exerciser clock for about 24 hours in case of
a power outage.
Recommended 9 volt alkaline batteries are (see Figure
5): Duracell MN 1404, Everready 522, Panasonic 6AM6
Turn on battery by putting S2 DIP switch actuator 10 in
the on position (up). See Table B and Figure 6.
Exercise with or without Load
The generator should be exercised under load or follow
the recommendations of the generator manufacturer. Be
sure the exerciser is turned on. Then select either
exercise with or without load. The ATS will transfer the
load to the generator when the exercise with load is
selected. See Figure 6 and Table B.
Table B. Generator Exercise Settings
Function
Factory
Setting
DIP
Switch
DIP
Actuator
Actuator
Position
clock
battery
off
S2
10
on (up)
off (down)
exerciser
off
S1
7
on (up)
off (down)
with load or
without load
without
load
S1
8
with (up)
without (down)
To Set Exerciser
Press and hold (5 seconds) the Set Engine Exerciser
button. The exercise period occurs immediately and at
approximately the same time weekly thereafter. The
status light below the button blinks during the exercise
period (including the cooldown). The light stays on to
indicate that the exerciser has been set. If the light is off,
the exerciser has not been set.
To Cancel an Active Exercise Period
Press the Bypass Time Delay button to stop an exercising
generator. If exercise with load is set, the ATS
retransfers the load to the utility, then stops the
generator after cooldown.