beautypg.com

Installation guide, For fusion shower pan surface mounted on conrete, Step 23 – Trending Accessibility Fusion shower pan surface mounted on concrete User Manual

Page 9: Best practice, Step 22, Step 21

background image

Installation Guide

www.trendingaccessibility.com

[email protected]

9

for fusion shower pan surface mounted on conrete

Step 22

Apply two coats of liquid waterproofing to achieve

2 mils. (roughly the thickness of a credit card)

Make sure that the “V” section of the gasket clamp

is filled with the liquid waterproofing.

Step 23

In order to set the correct height of the grate frame,

you may need to use the height extension ring

(see diagram to the right). If the height extension

ring is required, it will need to be fixed to the height

adjustment ring using solvent cement. The grate

frame can now be attached to the height adjustment

or extension ring, depending on tile thickness. This is

done by using firm pressure to clip the components

together; it is a tight fit.

“click”

1/4” to 5/8” Tile Height

5/8” - 1” Tile Height

extention ring

adjusting ring

grate frame

grate frame

adjusting ring

Best Practice

To achieve the best results, we recommend

waterproofing the whole room.

Step 21

Begin the application of the liquid waterproofing

membrane. Paint a layer of liquid waterproofing

over all taped joints. It is easiest to begin with the

walls first and then proceed to the floor area. For

consistant application, use a paint roller to apply

waterproofing to all surfaces. After first coat is dry,

re-coat.