T R O U B L E S H O O T I N G : G E N E R A L N O T E S

IF THE CONTROLLER IS NEWLY INSTALLED, CHECK THESE THINGS FIRST:

1) Re-check system wiring to insure proper installation and polarity.
2) Check all system fuses and circuit breakers. Before replacing a blown fuse, locate and correct

the cause.

3) Check to be sure that there is a connection (voltage input) to the "BATTERY VOLTAGE

SENSE" terminals from the battery. This would be either a factory installed jumper strip on the
regulator terminal block from the "BATTERY VOLTAGE SENSE" terminals to the "BATTERY"
terminals, or a connection from the sense terminals directly to the battery itself.

4) Check to see that modules and batteries are in the correct series-parallel configuration for

proper system voltage and current.

5) Review controller specifications relating to solar panel output, load ratings and system sizing

to insure that ratings are not exceeded.

6) Review the controller specifications relating to operation and set points, particularly the charge

termination and reconnect voltage set points. If possible, check this with the operation of the
controller, monitoring the battery voltage with a multi-meter.

7) Some types of loads (fluorescent lights, inverters) can generate electronic "noise" that

sometimes interferes with the operation of the controller. Check to see if strange behavior can
be traced to operation of a certain appliance.

8) If the unit is equipped with temperature compensation, inspect the temperature sensor and

sensor wire. Check for a broken sensor or a cut or frayed sensor wire.

9) If possible, perform the "FIELD TEST PROCEDURE" and/or "BENCH TEST PROCEDURE"

that follows.

10) The colored scale volt meters that the SC2 with F options are equipped with are 5% accurate

(about .5 volt in a 12 volt system) and are designed to give a general state of charge, not to
determine voltages accurately.

IF THE CONTROLLER HAS BEEN INSTALLED AND WORKING PROPERLY
FOR AWHILE, CHECK THESE THINGS FIRST:

11) Check all system fuses and circuit breakers. Before replacing a blown fuse, locate and

correct the cause.

12) Confirm that all connections are clean and tight. Particularly check crimp connections that

have been crimped but not soldered as these connections tend to deteriorate over time.

13) Some types of loads (fluorescent lights, inverters) can generate electronic "noise" that

sometimes interferes with the operation of the controller. Check to see if strange behavior can
be traced to operation of a certain appliance.

14) If you have an accurate digital volt meter, check for voltage drop between the regulator and

the battery by measuring voltage at the battery and at the regulator when maximum charging
is occurring. Drops often occur through old fuses, fuse holders or circuit breaker boxes and at
loose or corroded connections.

15) High voltage from nearby lightning strikes or unregulated charging sources can damage the

controller. The built-in lightning protection provides substantial protection, but it is sometimes
overwhelmed.

16) If the unit is equipped with temperature compensation, inspect the temperature sensor and

sensor wire. Check for a broken sensor or a cut or frayed sensor wire.

17) Check output from the solar panel, and that it is not partially shaded or dirty.
18) If possible, perform the "FIELD TEST PROCEDURE" and/or "BENCH TEST PROCEDURE"

that follows.