9 Hydraulic Installation

Ensure all pressure has been bled from the system before disconnecting any lines
or fittings. Hydraulic pressure will exist on the wing tilt circuits unless the wings
are being supported by other means. The hydraulic installation may be performed
with the wings in transport position, resting on the ground or with the tilt cylinders
fully extended.

Component failure due to oil contamination is not covered under the NORAC UC5
system warranty. It is recommended that a qualified technician perform the
hydraulic installation.

9.1

Valve Block Assembly

1. On a clean surface remove the plastic plugs from the block.

2. Install the 6MB (*F10) fittings into the “P” and “T” ports. Tighten to 18 ft-lbs (24 Nm).

3. Insert the two orifices (F06) into the “B” ports on the 2 station valve block. Note the

orifice orientation in Figure 17.

4. Install the 6MB-6MJ (F04) fittings into the “B” ports on the 2 station valve block. Tighten to

18 ft-lbs (24 Nm).

5. Install the 6MBP (F05) plugs into the “A” ports on the 2 station valve block. Tighten to 18

ft-lbs (24 Nm).

6. Insert orifice F06 into the “B” port on the 3

rd

station of the valve block with the notch

facing out.

7. Insert orifice F07 into the “A” port on the 3

rd

station of the valve block with the notch

facing in.

8. Install the 6MB-6MJ (F04) fittings into the “A” and “B” ports on the 3

rd

station of the valve

block. Tighten to 18 ft-lbs (24 Nm).