3 hydraulic plumbing – NORAC UC5-BC-JD12 User Manual
Page 31
28
10.3 Hydraulic Plumbing
From this point on in the installation the booms will be inoperative until the
hydraulics are fully installed.
1. After the NORAC valve is mounted, the hydraulic hoses and fittings can be plumbed. The
plumbing for the hydraulic circuit is shown schematically in Figure 3.
2. Install two 6MOR-6FORX90 fittings (F06) onto the “P” and “T” ports of the NORAC valve
block.
3. Connect the hoses (H01) to the 90 degree fittings (F06) on the pressure and tank ports on
the NORAC valve block (V01).
4. Install an 8FORXR-8MORT (F08) tee between the existing tank line and the sprayer valve
block.
5. Install a 6MOR-8FORX (F07) fitting onto the tee (F08). Install a 6MOR-6FORX90 fitting
(F06) onto the F07 fitting.
6. Connect the tank line (H01) from the NORAC valve block to the F06 fitting.
7. Install an 8FORXR-8MORT (F08) tee between the existing pressure line and the sprayer
valve block. The pressure port is located on the smaller valve block next to the main block.
8. Install a 6MOR-8FORX (F07) fitting onto the tee (F08). Install a 6MOR-6FORX90 fitting
(F06) onto the F07 fitting.
9. Connect the pressure line (H01) from the NORAC valve block to the F06 fitting.
10. Insert the 6FORXR-6MORT tees (F05) into the existing raise and lower lines at the wing
cylinders.
11. Install four 6MOR-6FORX90 fittings (F06) onto the 6FORXR-6MORT tees (F05).
12. Install four 6MOR-6FORX90 fittings (F06) onto the “A” and “B” ports of the NORAC valve
block.
13. Connect 4 hoses (H02) between the 90 degree fittings (F06).
14. The “raise” lines must be connected to the "B" ports of the NORAC valve block. The
“lower” lines of the cylinders must be connected to the "A" ports of the NORAC block.
15. Install a 6MOR-6FORX90 fitting (F06) onto the “B” port of the 3
rd
station of the NORAC
valve block.