4.6.2 Valve Mounting

1. Mount the NORAC valve (V01) on the

sprayer using the valve mounting
bracket (B10).

2. As shown in Figure 21, screw short

side of the threaded rods into the
bottom of the valve block at least 3/8".
The valve mounting holes are drilled and

tapped 3/8 NC-1" deep.

3. Tighten the Hex nuts to hold the rods.

4. Put the mounting bracket on the other

side of the tube and tighten with the
spring washers and the Hex nuts. Cut
excess off of the rods, if necessary.

If using bolts, the bolts should

thread into the valve block at
least 3/8". The valve mounting
holes are drilled and tapped 3/8

NC-1" deep. The rule of thumb
for bolt length is 1-1/2" longer
than the tube size.

You must ensure no hydraulic

components will interfere with
any sprayer parts or be pulled
tight at any time.

Figure 21: Valve Mounting Location

4.6.3 Hydraulic Plumbing

WARNING!

From this point in the installation the
booms will be inoperative until the
electronics are fully installed.

1. After the NORAC valves are mounted,

the hydraulic hoses and fittings can be
plumbed. The plumbing for the hydraulic
circuit is shown schematically in Figure
3
.

2. The “raise” lines from the rod end of

the cylinders must be connected to the

“B” ports of the NORAC valve block.