2 valve mounting, 3 hydraulic plumbing – NORAC UC4+BC+RG7 User Manual
Page 22
19
4.6.2 Valve Mounting
1. Mount the NORAC valve (V01) on the
sprayer using the valve mounting
bracket (B10).
2. As shown in Figure 21, screw short
side of the threaded rods into the
bottom of the valve block at least 3/8".
The valve mounting holes are drilled and
tapped 3/8 NC-1" deep.
3. Tighten the Hex nuts to hold the rods.
4. Put the mounting bracket on the other
side of the tube and tighten with the
spring washers and the Hex nuts. Cut
excess off of the rods, if necessary.
If using bolts, the bolts should
thread into the valve block at
least 3/8". The valve mounting
holes are drilled and tapped 3/8
NC-1" deep. The rule of thumb
for bolt length is 1-1/2" longer
than the tube size.
You must ensure no hydraulic
components will interfere with
any sprayer parts or be pulled
tight at any time.
Figure 21: Valve Mounting Location
4.6.3 Hydraulic Plumbing
WARNING!
From this point in the installation the
booms will be inoperative until the
electronics are fully installed.
1. After the NORAC valves are mounted,
the hydraulic hoses and fittings can be
plumbed. The plumbing for the hydraulic
circuit is shown schematically in Figure
3.
2. The “raise” lines from the rod end of
the cylinders must be connected to the
“B” ports of the NORAC valve block.