26

12. Connect the six pin shroud (T6B) on cable

C17 to the mating tower on the valve
extension cable (C11).

13. Connect the three pin tower (T3) on cable

C17 to the mating tower on the valve
extension cable (C11).

Two connectors on C17 will remain

disconnected. These are used when
installing other UC4+ options.

14. Install the two 2-pin connectors on the end

of cable C17 to the 3

rd

station of the block

as per Figure 34.

The connector marked “Main Down”

goes on the same side of the block as
the hoses.

15. Connect the CAN Node cable (C02B) to

P4 on the valve extension cable (C11).

16. Route the CAN Node cable (C02B) to the

two roll sensors which are installed in
Section 4.5. Follow existing cables and/or
hydraulic lines.

17. Connect the 4-pin AMP connectors on

C02B to the roll sensors.

18. Connect the sensor branch cable (C02) to

the 4-pin AMP plug on C02B.

19. Route the sensor branch cable (C02) to the

wing and main sensors and connect to the
sensors. Follow existing cables and/or

hydraulic lines along the boom.

Route the main lift cable through the

main lift mounting bracket tube to
provide additional cable protection

20. Cable-tie the installed cables every 12

inches.

Figure 36: Cable Configurations: C11, C02

and C02B

IMPORTANT:

Provide enough slack in all cables to
account for the movement of the main
section, parallel lift, and FOLDING boom
movement.