beautypg.com

8 completing the installation – NORAC UC4+BC+FC1 User Manual

Page 26

background image

23

4.8 C

OMPLETING THE

I

NSTALLATION

1. Start up your sprayer and test the

sprayer’s functionality. The NORAC
Control Panel does not need to be
powered up for the original switches to
function. Unfold the booms and
raise/lower each boom and main
section.

Confirm that the cabling and

hoses are agreeable to the entire
range of motion.

2. If any functions do not work, review the

hydraulic and electrical portions of this
manual to check for proper installation.
If you still have trouble, contact
NORAC for assistance.

3. Turn on the power for the UC4+

Control Panel using the switch on the

side of its chassis.

4. Repeat the Boom Speed Test as

described in Section 4.2 Boom Speed
Test
with the NORAC UC4+ System
installed. Record the results for
comparison in Table 5.

5. For optimal performance of the UC4

system, there should be very little play
at the hitch clevis. The addition of
polymer washers can help tighten up
this connection (Figure 28).

Figure 28: Hitch Point

6. The procedure for the installation of the

UC4+ System is now complete. Begin
the AUTOMATIC SYSTEM SETUP
procedure as described in the UC4+
Sprayer Boom Control Operator’s
Manual
(M01).