beautypg.com

NORAC UC4+BC+FC1 User Manual

Page 25

background image

22

9. Install the 2-pin connectors from C03

onto each NORAC valve as shown in
Figure 26.

10. The connectors on the valve cable

(C03) are marked RIGHT UP, LEFT
UP
, RIGHT DOWN and LEFT
DOWN
. Cables labeled with UP go
on the same side as the hydraulic hoses.

Figure 26: Valve Cable Connections

11. Connect the CAN Node cable (C02B)

to the 4-pin AMP plug on C01.

12. Route the CAN Node cable (C02B) to

the roll sensors. Follow existing cables
and/or hydraulic lines.

Figure 27: Cable Configurations: C01,

C02, C02B, C03 and C04

13. Connect the sensor branch cable (C02)

to the 4-pin AMP plug on C02B.

14. Route the sensor branch cable (C02) to

the wing and main sensors. Follow
existing cables and/or hydraulic lines
along the boom.

15. Cable-tie the installed cables every 12

inches.

IMPORTANT:

Provide enough slack in all cables to
account for the movement of the
main section, parallel lift, and

FOLDING boom movement.