beautypg.com

7 | maintenance, 6 | commissioning – GEA Bock HGX46 CO2 T User Manual

Page 32

background image

32

D
GB
F
E

96259-12.2014-DGb

6.9 Avoid slugging

7.1 Preparation

7| Maintenance

To prevent slugging:

The complete refrigeration plant must be properly designed.
All components must be compatibly rated with each other with regard to output (particularly the

evaporator and expansion valves).

Suction gas superheating at the compressor input

should be > 10 K (check the setting of the

expansion valve).

The system must reach a state of equilibrium.
Particularly in critical systems (e.g. several evaporator points), measures such as the use of liquid

traps, solenoid valve in the liquid line, etc. are recommended.
There should be no movement of refrigerant in the compressor while the system is at a
standstill.

Regard oil temperature and pressure gas temperature (the pressure gas temperature has to be

high enough, so the oil temperature is > 30°C.

ATTENTION Slugging can result in damage to the compressor and cause

refrigerant to leak.

WARNING

Before starting any work on the compressor:

Switch off the compressor and secure it to prevent a restart.
Relieve compressor of system pressure.
Prevent air from infiltrating the system!

After maintenance has been performed:

Connect safety switch.
Evacuate compressor.
Release switch-on lock.

WARNING

The decompression has to be carried out in a way that no dry ice
respectively solid CO

2

is produced which blocks the outlet and

could hinder the streaming out of CO

2

. Otherwise, there is the dan-

ger that pressure can be built up again.

6| Commissioning