3.6.6 TOOLS

→ TEST → VALIDATE CM 2000

The Validate CM 2000 operation is invoked by selecting the Test and Validate CM 2000
option from the Tools menu. A validation window is shown in Figure 3-10.

Figure 3-10 – Validate CM 2000 Form, Initial Screen

Push the Start command button to show the Dialog boxes for the Unit Type, the
Configuration Parameters, and the Stabilization Calibration as shown in Figure 3-11. The
user must respond to these questions for the test to continue. At the end of the test, a
summary of the results is shown as in Figure 3-12.

Figure 3-11 – Validate CM 2000 Form, Configuration Screen

Figure 3-12 – Validate CM 2000 Form, Conclusion Screen