SECTION 7.

7A Filling the System

It is crucial to the efficient operation of the system

that all air be removed from the circuit. For this

reason, an air scoop and vent should be located close

to the boiler outlet, and there should be a minimum

distance between cold water feed and system purge

valve.
1. When the system has been completely installed,

close all air vents and open the makeup water

valve. Allow the circuit to fill slowly.

2. If a make-up water pump is employed, adjust the

pressure to provide a minimum of 12 psi (83kPa)

at the highest point in the circuit. If a pressure

regulator is also installed in the line, adjust it to

the same pressure.

3. Close all valves. Purge one circuit at a time as

follows:

a. Open one circuit drain valve and let water

drain out for at least 5 minutes. Be certain

there are no air bubbles visible in the water

stream before closing the drain valve.

b. Repeat this procedure for each circuit.

4. Open all valves after all circuits have been

purged.

5. Run the system circulating pump for a minimum

of 30 minutes with the boiler shut off.

6. Open all strainers in the system, and check for

debris.

7. Recheck all air vents as described in Step 3.
8. Inspect the liquid level in the expansion tank,

with the system full of water, and under normal

operating pressure, to ensure proper water level

in the expansion tank.

9. Start up boiler according to the procedures

described in Section 2 and operate the system,

including the pump, boiler, and radiation units,

for one hour.

10. Recheck the water level in the expansion tank. If

it exceeds 1/2 of the volume of the tank, open the

tank drain and reduce the water level.

11. Shut down the entire system, and vent all

radiation units and high points in the system.

12. Close the water makeup valve and check the

strainer in the pressure reducing valve for

sediment or debris. Reopen the water makeup

valve.

13. Verify system pressure with the boiler pressure

gauge before beginning regular operation.

14. Within 3 days of start-up, recheck and bleed

all air vents and the expansion tank using these

instructions.