Inspection and start-up checklists, Handling and installing, Starting-up the unit – Wine Guardian Ducted Split Wine Cellar Cooling Systems (WGS175) - Manual User Manual
Page 58

60
Inspection and Start-up Checklists
Unit received
Unit received complete as ordered including accessories
Handling and Installing
Unit mounted on solid level surface
Sufficient space allowed for access to unit and accessories
Proper electrical service provided
Hot water provided to humidifier
Drain lines and trap installed properly
Ductwork, fittings and grilles installed properly
All cold duct surfaces insulated
Low ambient control included if freezing condition present
No obstructions to air flow to condenser
Starting-up the Unit
General visual inspection looks good
All wiring connections checked
All ducts, grilles and panels in place
Start unit
Check ducts and connections for air leaks
Balance air distribution
Confirm condenser airflow is unrestricted
Verify cooling and heating operation
Check for excessive noise or vibration