Commissioning
Project transfer to the operating unit
Project download
l
56
EDBPM−H310 DE/EN/FR 7.1
5.2.2
Project download
)
Note!
In the »HMI Designer« you can select whether you want to update
the firmware at the time the project is loaded.
The firmware must always be updated with the first download of a
project to the operating unit or after an update of the
»HMI Designer« planning tool.
I
Tip!
Sample projects for the operating unit can be found in the
»HMI Designer« planning tool under File
W Open... W Samples.
0
shift
F1
Esc
F2
F3
F4
F5
Help
Info
h310_007
How to download a project into the operating unit:
1. Switch on your PC and start the «HMI Designer» planning tool.
2. Switch on the operating unit:
A. Keep the enter key
0
of the operating unit pressed.
B. Switch on the supply voltage for the operating unit.
C. Let go of the enter key
0
when H310 Service Page" appears on the
display.
3. Load the desired project from the HMI Designer into the operating unit.
–
See HMI Designer − Getting started" Manual.
After the download, the operating unit is ready for operation and can exchange