Start up & operation – Kifco E23 360,000 - Present: Operator Manual User Manual
Page 16
T23_AA_Operator Manual_2014
Revised 08/2014
Start Up & Operation
Step-by Step Operation Continued
10. Verify that the coils of tube remaining on the drum are both coiled and packed
tightly (photo). If they are not use the hand crank and PTO input on the gearbox to
tighten them.
11. Attach supply hose. Verify there are no kinks or twists in the supply hose.
12. Lower the anti reverse pawl prior to engaging the drive system.
13. Verify the turbine is off and turn on your pump. If your supply lines have not been used for an extended
period of time, flush them prior to attaching to the Water-Reel.
14. Engage the gear box via the clutch pin.
15. After all air is purged from the system and the sprinkler is operating smoothly allow water to go through
the system for several minutes to carry out any trash or debris that may have been in the mainline pipe.
After the system is thoroughly flushed, start the drive system by engaging the turbine.
Turbine Drive
Engage turbine and adjust speed control knob
after system is purged.
Warning! Do not pick up or hold
supply hose as it is being pressurized!
Engaged Position
Disengaged Position
Start
Stop
13