beautypg.com

Start up & operation – Kifco E23 360,000 - Present: Operator Manual User Manual

Page 14

background image

T23_AA_Operator Manual_2014

Revised 08/2014

Start Up & Operation

Step-by Step Operation Continued


2. Lower the stabilizer legs. Remove the cotter pin to the slide bolt holding the stabilizer leg in position while

holding the handle. Lower each leg into the ground and firmly stomp them into the ground. Replace the
slide bolt & cotter pin once lowered.







Warning!

Never operate the Water-Reel with only one stabilizer

leg in the ground or without the stabilizer feet firmly inserted in the
ground.

3. AA models are equipped with a standard hand crank jack for making height

adjustments. Lower the jack and level your unit, unhook and pull tractor around
into position to pull sprinkler cart down the irrigation lane.

1. Verify that the chassis of your Ag-Rain Water-Reel is level, if not adjust the jack

accordingly. Also verify that both stabilizer legs are securely in the ground.

2. Adjust sprinkler cart to the desired width. See “Specification” section.

3. Lower the sprinkler cart from its transport position. Set the desired sprinkler arc and confirm that the sprin-

kler is equipped with the proper nozzle. Note: Turbine drive irrigators have a minimum G.P.M. flow
requirement. Do not attempt to operate at flows or pressures different from those
listed on the “Performance Guide” decal that is installed on the machine.

4. Lift Anti-Return pawl (Diagram below). Flip the pawl into the up position.

Important! If the pawl is under pressure, remove the safety guard and the yellow sleeve on the gearbox PTO
shaft and remove the key that locks the shaft into position.

Anti-Return Pawl

Remove Safety Shield

Remove Yellow Sleeve

Close up of Locking Key in
Shaft

Remove Locking Key

11