Soft ceiling tile installation, Occupancy sensor – ETC Unison Paradigm Occupancy Sensor User Manual
Page 4

E T C I n s t a l l a t i o n G u i d e
Occupancy Sensor
Occupancy Sensor Installation Guide
Page 4 of 8
Electronic Theatre Controls, Inc.
Soft Ceiling Tile Installation
Step 1:Pull the Belden 8471 (or equivalent) and 14 AWG (2.5mm
2
) ground wire to the
installation location.
Step 2:Orient the smooth side of the mounting plate to the ceiling tile and insert the
soft ceiling tile adaptor through the two small holes near the center of the
mounting plate.
Step 3:Poke the adaptor tines through the ceiling tile, then bend each tine over in
opposite directions for a secure fit.
Step 4:If you are installing the sensor in series with other sensors or stations
(continuing the data run), use the provided LinkConnect pigtail, ESD ground
wire pigtail and WAGO connectors to make the terminations. If you are not
continuing the data run, proceed to step 5.
poke the adapter through the ceiling tile, then bend
it over for a secure fit.
LinkConnect pigtail and
WAGO connectors
(optional use)
terminate
wires here
install
ed control
wire
installed control wire to next stati
on
sensor pigtail
a: Strip 3/16” (5mm) of insulation from each installed wire.
b: Open the three terminal levers on a WAGO connector
and insert the installed (typically black) Belden 8471
LinkConnect wire, the black lead from the sensor pigtail,
and the continuing Belden 8471 (typically black) wire
into the terminals.
c: Close the levers onto the wires.
d: Repeat the above for the installed (typically white)
Belden 8471 LinkConnect wire and the remaining pigtail
from the sensor, as well as the ESD ground wires using
a new WAGO connector for each termination type.