24
controls and that restarting is prevented until all stop switches are unlatched.
The unit must have a thorough inspection carried out every 6 months
in accordance with LOLER Regulations 1998 or your relevant national
regulations and a Certificate of Thorough Inspection produced by a
competent person.
Always ensure the machine structure is in good, sound, undamaged
condition. Any inspection procedure is always aided by keeping the
machine clean.
NB. Do not steam clean the battery charger or electrical
components.
!
Weekly Checks.
1. Apply grease to the slew gear wheel and all grease nipples.
2. Check battery acid level, top up with distilled water if required (maximum 6mm over
plates when battery is standing level), and check mains cable wiring.
Monthly Checks.
1. Thorough machine inspection to be carried out by a trained and competent person.
Complete daily and weekly checks and the following.
Slew Drive
MAINTENANCE