To power on the switch, perform the following procedure:

1. Plug the power cord into the AC power connector on the back of the

switch, as shown in Figure 19.

Figure 19. Plugging in the AC Power Cord

2. Plug the other end of the power cord into a wall outlet.

3. Verify that the POWER LED is green. If the LED is off, refer to

Chapter 3, “Troubleshooting” on page 51.

The switch is now powered on and ready for network operations. To
start a local management session on the switch, refer to “Starting a
Management Session” on page 49