Page 7

Operating and installation instructions

Liquid return temperature limiter

5.4 Steam trap testing through ultrasonic measurement

Testing the operation of the steam trap in the installed state is straightforward with the
“ARImetec

®

-S” multifunction tester.

Refer to data sheet „ARImetec

®

-S“.

5.5 Installation position

The preferred installation position for the steam trap is horizontal, but inclined positions of
the screw cap (Pos. 6) are possible.

6.0 Putting the valve into operation

ATTENTION !
- Before putting the valve into operation, check material, pressure, temperature

and direction of flow.

- Regional safety instructions must be adhered to.
- Residues in piping and valves (dirt, weld beads, etc.) inevitably lead to leakage.
- Touching the valve when it is operating at high (> 50 °C) or low (< 0 °C) media

temperatures can cause injury.
Affix warning notice or protective insulation as appropriate!

Before putting a new plant into operation or restarting a plant after repairs or
modification, always make sure that:
- All works has been completed!
- The valve is in the correct position for its function.
- Safety devices have been attached.