7.0 Care and maintenance

Maintenance work and intervals must be defined by the operator according to the service
conditions.

7.1 Replacing the valve stem seals

7.1.1 PTFE V-ring unit design

PTFE V-ring unit (pos. 12) consisting of:

1 backing ring
4 sealing rings
1 cover ring

This stem seal is self-adjusting owing to the built-in
compression spring (pos. 15). If the stem begins to
leak, the seal pack is worn out and must be replaced.

To replace the PTFE V-ring unit:

- Remove the actuator (refer to section 10.1).

- When replacing the PTFE V-ring unit (pos. 12), make

sure that all parts are installed in the correct order
and position (refer to Fig. 4).

- The gasket (pos. 17) must be replaced.

Note:
Damaged stems must also be replaced (refer to
section 7.2 for instructions) because a new seal pack
will soon begin to leak again if the stem is no longer
intact.

- To assemble the actuator, refer to section 7.5.

ATTENTION !
Refer to sections 10.0 and 11.0 before
dismantling the valve.

Fig. 4: PTFE V-ring unit