beautypg.com

0 dismantling the valve, 1 dismantling the actuator from the valve, 2 dismantling the actuator – ARI Armaturen STEVI BBD 415 DN 25-50 EN User Manual

Page 16: 0 dismantling the valve -16, Efer to section 10.1), Tuator (refer to section 10.2), Ns 10.0 and 1

background image

Page 2-16

Rev. 0040321000 0714

Operating and Installation Instructions

Straight-through blow-down valves - STEVI

®

BBD 415

10.0 Dismantling the valve

10.1 Dismantling the actuator from the valve

- Move the actuator into the upper travel position with control air pressure.
- Loosen the lock nut (pos. 21).
- Unscrew the valve stem (pos. 5) from the actuator stem (pos. 50.1).
- Loosen the fastening nuts (pos. 52).
- Dismantle the actuator from the valve.

10.2 Dismantling the actuator

- Reduce the control air pressure to "0" and disconnect the control air line from the

compressed air system.

- Loosen the screws (pos. 50.21) on the actuator and remove the diaphragm cover

(pos. 50.18).

ATTENTION !
Check the following points carefully:
- The piping system must be pressureless.
- The medium must be cool.
- The plant must be drained.
- The piping system must be purged of all caustic, inflammable, aggressive or

toxic media.

ATTENTION !
- The longer screws (pos. 50.23) should be loosened last symmetrically in order

to reduce the spring pre-tension gradually.

- The order described above must be observed to prevent injury to persons.