Power verification, Verification of electrical ds3 power level, Installing the d3 – ADC DL3XR-FCA100 User Manual
Page 20: Ower, Erification
Installing a D3LX CO Module in an LEC
LTPS-UM-8013-03
12
August 30, 2002
D3LX CO and RMT Modules
Figure 7.
Installing the D3LX CO
9
After removing the protective cover from a fiber patch cord, clean the fiber-optic connector and adapter as
directed in
“Appendix B - Cleaning and Mating Fiber-Optic Systems” on page 39
.
P
OWER
V
ERIFICATION
Verification of Electrical DS3 Power Level
1
Apply power to the D3LX CO.
2
Attach the fiber patch cord from the D3LX CO to a meter.
3
Confirm that the readings are within the specification (-5 dBm to -23 dBm).
If the reading is not within the specification, check all fiber-optic connections to the D3LX CO.
If the reading is still not within the specification, replace the module.
4
Once the readings are within specification, disconnect the patch cord from the meter.
Now that the DS3 power level meets optical specifications, verify the D3LX CO module.