4.7 Electrical connection

Electrical connection must be performed by a master electrician,

only after the cable has been installed and encased in concrete

and the curing of concrete period is complete.

WARNING! DANGER OF ELECTROCUTION: always make sure

the power supply circuit is turned off before proceeding with

the electrical connection.

1. Measure the resistance and cable insulation and record these values on line # 4 of the measurement chart

on the electrical panel label.

2. Use a control device from Ouellet to perform the connection of the OWC-M concrete cable system. Refer

to section 5 to help assist you in the selection of a suitable control device for your installation.

3. Perform the connection in compliance with instructions provided in Ouellet’s operating guides for controls

and in compliance with local and national electrical specifications in effect.

240/208V and 347V connection:
Line 1 - black
Line 2 - red
Ground – yellow/green

4. For installations requiring more than one electric circuit, obtain an adequate control kit from Ouellet which

includes a master thermostat as well as a sufficient number of slaves depending on the system’s power.

5. Lastly, identify the circuits at the electrical panel and stick the completed label to the electrical panel which

includes all the measurements taken during the installation process.

Do not power up the OWC-M concrete cable system

before the concrete curing process is complete in accordance

with the manufacturer’s recommendations

(check with the concrete supplier).

4.8 Putting into service

When the OWC-M concrete cable system is ready to be put into service, activate the circuit breaker and set
the temperature according to your desired level of comfort.

WARNING!

WARNING!

Image 25