Restart procedure, Power application – American Power Conversion 200/208 V User Manual
Page 31
990-2359A
Smart-UPS® VT 10-30kVA, 200/208V and XR Battery Enclosure Operation Guide
23
Restart Procedure
Power application
Set the utility breaker to the ON position.
If your installation includes an XR Battery Enclosure with a DC disconnect switch, set the DC
disconnect switch to the ON position.
After system boot-up, the display will automatically prompt you on how to confirm/select voltage
and frequency as shown in the following.
WARNING!
Only trained personnel familiar with the construction and the equipment may carry out
the Start-Up procedure.
NOTE!
Wait approximately 30 seconds for the system to boot up and carry out self test.
XR Battery Enclosure
Utility
breaker
UPS
See also other documents in the category American Power Conversion Tools:
- 5000VA (25 pages)
- MX28B-400 (46 pages)
- CTEG4-240MB-5 (7 pages)
- VS 100 (54 pages)
- SMARTUPS 700 (60 pages)
- AP7562J (24 pages)
- 100VAC (18 pages)
- Smart-UPS VT (56 pages)
- 1400XLT (30 pages)
- 350/550 (2 pages)
- SURTA1500XLJ (16 pages)
- RT-UXI (20 pages)
- 2200 VA (17 pages)
- 208 Vac (17 pages)
- 1500VA (18 pages)
- Smart-UPS (36 pages)
- 60-80kW 208/480V (34 pages)
- 420 (3 pages)
- 220 VAC (21 pages)
- 350 (2 pages)
- AP9215 (20 pages)
- Back-UPS CS 500 (2 pages)
- PDU (54 pages)
- Airless Paint Sprayer 68001 (24 pages)
- AP7610 (16 pages)
- AP7902 AP7911 (26 pages)
- UPS (2 pages)
- RT XLI/XLICH (34 pages)
- 990-2233A (19 pages)
- 208/220 (48 pages)
- NS 600 (2 pages)
- SYMF800KH (54 pages)
- 20-30 kVA 480V (4 pages)
- 100 VAC (25 pages)
- 750 (17 pages)
- 3000 (23 pages)
- MX28B200 (61 pages)
- RS 1000 (2 pages)
- 200-240 VAC (21 pages)
- 5000RMB (23 pages)
- 480kW400V (32 pages)
- AP9825I (1 page)
- 250/450 (2 pages)
- SUA48RMXLBP3U (8 pages)