beautypg.com

Restart procedure, Power application – American Power Conversion 200/208 V User Manual

Page 31

background image

990-2359A

Smart-UPS® VT 10-30kVA, 200/208V and XR Battery Enclosure Operation Guide

23

Restart Procedure

Power application

Set the utility breaker to the ON position.

If your installation includes an XR Battery Enclosure with a DC disconnect switch, set the DC
disconnect switch to the ON position.

After system boot-up, the display will automatically prompt you on how to confirm/select voltage
and frequency as shown in the following.

WARNING!
Only trained personnel familiar with the construction and the equipment may carry out
the Start-Up procedure.

NOTE!
Wait approximately 30 seconds for the system to boot up and carry out self test.

XR Battery Enclosure

Utility
breaker

UPS