Commissioning Procedure
COMMISSIONING CHECKLIST
The following should be carried out with a load on the system; otherwise the unit is likely
to short cycle. The following tests are to be carried out on 1 circuit at a time.
Switch the door interlocking MCCB to the ON position but again only on the circuit
which is to be tested
Adjust the water temperature supply and return set points to match the
system requirements
To switch the unit ON, use the microprocessor keypad as follows:
Press
Prg
, press
, press
, press
& finally
Check liquid injection solenoid valve is energised and sight glass is clear
Check pressures at suction and discharge ports for correct phase rotation
CAUTION
If there is no liquid present or no differential pressure occurs, isolate immediately.
RECORD
Check the unloading solenoids operate in the correct sequence - refer to
Measure and record the compressor amps once the compressors are fully loaded
and then at each of the unloading stage
Measure and record full speed amps of each condenser
CAUTION
The microprocessor LP setting is adjustable via the micro display. It is
recommended that this setting be 0.6 bar below the equipment freezing point of the
cooling medium ie for water (no glycol) LP micro settings is 3.2barg.
Ensure that the low water temperature safety cuts out at the correct setting +/- 0.5°C,
to clear the alarms refer to
For water (no glycol) application, the recommended setting is 3°C below the design
supply water temperature (to a minimum of 3°C)
RECORD
Check the liquid line sight glass is clear and dry
Check the superheat setting adjust the expansion valve to maintain a superheat
setting of 5 - 8°C at all operating loads
Check and record the following:
Suction and discharge pressures
Liquid, discharge and suction line temperature
Water inlet and outlet temperature
Ensure the above are all within the design parameters
Repeat as follows for each circuit:
To switch the unit OFF, use the microprocessor keypad as follows:
Press
Prg
, press
, press
, press
& finally
To switch the unit ON, repeat above
The unit is now commissioned and will provide many years of trouble free operation
providing the following maintenance schedule is followed.