10.1 Start-up report

Please complete this start-up checklist and return it to the manufacturer.

WARNING!
Complete the start-up checklist before you energize the device.

Yes

Yes

Yes

Yes

No

No

No

No

Are the polarity and the supply voltage correct?

Ex-approved devices only: does the device and the installation agrees with the

requirements of the Ex certificate of compliance?

Are all the wetted components (probe, flange and gaskets) resistant to the product in the

tank?

Does the information on the signal converter nameplate agree with the operating data?

Are the process temperature and pressure in the limits for operation of the device?

Did you correctly install the device on the tank?

Do the electrical connections agree with the national electrical codes?