Run method, Run direct measurement, Run manual dosing – Hach-Lange TITRALAB Users Guide User Manual
Page 69

Running analyses
69
Run method
Run method
Run method
Run method
Run method
Refer to Short-Form Reminder no. 6.
1.
Select the method in the Method library.
2.
Install the electrode then the reagent groups to be used to perform
the analysis.
3.
Display the Main window.
4.
Press 1 to start the analysis.
Run direct measurement
Run direct measurement
Run direct measurement
Run direct measurement
Run direct measurement
Refer to Short-Form Reminder no. 8.
1.
Select the method.
2.
Install the electrode group to be used to perform the measurement.
3.
Prepare the sample solution and place on the sample stand.
4.
Display the Electrodes window.
5.
Press 5 to start the measurement.
6.
Select the electrode in the list of connected electrodes. You can
stop or start stirring by pressing 1.
Run manual dosing
Run manual dosing
Run manual dosing
Run manual dosing
Run manual dosing
Refer to Short-Form Reminder no. 10.
1.
Select the method.
2.
Install the electrode group to be used to perform the measurement
(if measurements are to be done).
3.
Install the reagent group to be used to perform the manual dosing.
4.
Prepare the sample solution and place on the sample stand.
5.
Display the Reagents window and press 5.
6.
Select the reagent in the list of installed reagents and select the
electrode in the list of connected electrodes (if measurements are to
be done).
7.
Enter an increment size, increment speed and maximum volume to
be dosed.