8. Wait until water comes out of the bleed valve and then close the

bleed connection.

CAUTION

The water may still be hot.

9. Switch on the boiler. A vent cycle of a duration of around 3 minutes

is carried out automatically.

10.After venting, check whether the pressure in the installation is still

sufficient.

If the water pressure is lower than 0,8 bar, more water

should be added. If necessary, top up the water level in the

heating system (recommended hydraulic pressure

between 1,5 and 2,0 bar).
¼ See chapter: "Filling the system", page 26

11.Set the heating set point.

5.5

Draining the installation

It may become necessary to empty the water from the heating system

when the radiators have to be replaced, should there be a major water

leak or a risk of frost. To do this, proceed as follows:
1. Open the valves on all radiators connected to the heating system.

2. Switch off the boiler electrical power supply.
3. Wait around 10 minutes until the radiators are cold.