Commissioning
610.44440.40.000
20 / 32
© Gardner Denver Deutschland GmbH
Take measures to ensure that the unit
CANNOT be operated with the shut-off device
closed.
Measure the motor insulation resistance.
At values ≤ 1kΩ / Volt of measurement poten-
tial, dry the windings.
Check the piping / hose connections for leaks.
6.2
Start-up of unit with operating-liquid
supply
Filling up with operating-liquid
For operation with supply of the operating-liquid,
now fill the unit's operating chamber with operat-
ing-liquid.
For automatically controlled operation:
the shut-off valve in the bypass line (item 5,
Fig. 8, page 17) is to be opened for approx.
20 s.
For non-automatic control of operation:
the shut-off valve (item 5, Fig. 9, page 17) is
to be opened for approx. 20 s.
Setting the initial pressure of the operating-
liquid
The initial pressure, p
A
in operating-liquid
supply line (item B, Fig. 11, page20) is to be
set at approx. 1 bar [14.5 psi] above the suc-
tion pressure, p
B
in the suction line (item A,
Fig. 11, page20).
B
A
pB = pA + 1 bar
pB = pA + 14.5 psi
610.44440.99.B14
A Suction line
B Operating-liquid supply line
Fig. 13: Adjusting the operating-liquid flow-rate:
setting the initial pressure
Further steps at start-up are identical to the pro-
cedures during operation.
6.3
Start-up of unit with self-suction of op-
erating-liquid
Fill up with operating-liquid
Units with self-suction of operating-liquid are filled
with operating-liquid before completion of the
installation (Filling up with operating-liquid,
page 15.
Further steps at start-up are identical to the pro-
cedures during operation.
6.4
Checking the direction of rotation
Check the piping / hose connections on the
suction and discharge connections.
The unit may not run dry!
See the section, "Filling up with operating-
liquid", page 15 and page 20.
Briefly switch the unit on then off again.
The intended direction of shaft rotation is
marked by an arrow (item 9 page 3) on the
pump casing.
Before shutting the unit down compare the
actual direction of rotation of the external fan
with the intended direction of rotation of the
shaft.
If necessary, reverse the direction of rotation
of the motor.