6.2
Checks before the first run
1
Check that the main power is switched off.
2
When installing a new unit, disconnect the motor (U / T1, V /
T2, W / T3) cables to prevent damage to the frequency
converter.
Measure the insulation resistance of the motor windings
(each phase to ground). Insulation resistance requirement for
new motor:
Cold motor (10..40 °C):
≥
5 M
Ω
Warm motor (40 °C or more):
≥
1 M
Ω
If insulation resistance is less that requirement the motor
shall be dried.
3
Reconnect the motor cables and check the thightness of the
other cables.
4
Check that the external connections and selected control
parameters (switches) are set according to the application.