4. Installation

14

PNEG-1735 U-Trough Direct Gear Drive Bin Sweep Auger Unload Systems

Figure 4G U-Trough Unload

Installation in Concrete Foundation

Concrete Knock-out

1. When constructing the concrete foundation, form a knock-out for the unload as shown

in Figure 4H

on Page 15

. This is the prefered method of installing the unload in concrete. When installed in this

manner unloads can be removed at a later date.

2. Cross section of foundation knock-out.

a. Center the unload in the bin foundation.

b. Anchor to the bottom of the knock-out with concrete anchor bolts (not provided).

c. Install floor flanges over the gates.

d. Use wood or metal planking to cover exposed unload between gates.