Chapter 7: Roof Assembly

Guidelines for Assembling and Lifting the A-Frame Rafter Sections

The roof is assembled in sections and referred to as A-frame rafter sections. Each A-frame rafter section is
assembled on the ground and lifted into place.

IMPORTANT: Do not drill additional holes in purlins. Install the flange bolts and nuts as dictated by the

number of holes in the purlin.

NOTE: Use purlin clips as lifting points, as shown.

Figure 7-20 Recommended lifting points for A-frame sections

A

Purlin clip

The A-frame rafter section has two configurations: with X-bracing and without. The number of A-frame
rafter sections with X-bracing depends on which size bin is being constructed.

DANGER

All lifting should be performed by a certified crane operator with prior bin
construction experience. Never lift during windy conditions.

General Guidelines:

• Construct the A-frame sections on flat ground or blocking.

• Install the temperature cable brackets at the same time you assemble the A-frame sections.

96

Pneg-4078 78 Ft Diameter 40-Series Bin