Chapter 7: Roof Assembly

Table 7-1 A-frame installation sequence and temperature cable locations for 78 ft diameter bin

A-frame number

Rafter Number

Temp Cable Number

Radius Location

A1

R1

R2

T13

28.6 ft

A2

R11

T7

28.6 ft

R12

A3

R21

R22

T11

28.6 ft

A4

R15

R16

A5

R5

T5

14 ft

R6

A6

R9

R10

A7

R23

R24

A8

R19

T3

14 ft

R20

T10

28.6 ft

A9

R3

R4

T14

28.6 ft

A10

R17

T9

28.6 ft

R18

A11

R7

R8

T6

28.6

A12

R13

T2

14 ft

R14

T8

28.6 ft

A13

R25

T12

28.6 ft

R26

T4

14 ft

NA

Attach to center collar

T1

5 ft

NOTE: A-frames labeled “A1” through “A5” have X-bracing and are installed first. A-frames labeled “A6”

through “A13” are standard A-frames. The empty spaces that are not labeled must have purlins
installed between the rafters after all the A-frames are secured. The numbers reflect the recom-
mended installation sequence of the A-frame assemblies.

Table 7-2 Starting lengths for temperature cables for 78 ft diameter bins

Length from the center collar

226.7 in. (575.82 cm)

Length from 14 ft diameter location

166.8 in. (423.67 cm)

Length from 28.6 ft diameter location

62.6 in. (159 cm)

The temperature cable lengths in the chart above are the distances from where the temperature cable
attaches to the rafter or the center collar to the top ring. To calculate the correct temperature cable length,
add 32 inches for each bin ring to the starting length. Temperature cables must terminate above any
unload equipment and be secured in place with twine. DO NOT allow cables to become tangled in unload
equipment.

Pneg-4078 78 Ft Diameter 40-Series Bin