beautypg.com

Chapter 7: roof assembly – Grain Systems Tanks PNEG-4078 User Manual

Page 104

background image

Chapter 7: Roof Assembly

1. With assistance, position a lower roof panel (A) onto the first rafter in any A-frame.

2. Install five flange bolts (D) and five flange nuts (E) into the lower portion of the lower roof panel secur-

ing the lower roof panel to the eave angle.

3. With assistance, position another lower roof panel (A) onto the next rafter in the A-frame.

NOTE: There should be an exposed gap between the two lower roof panels in the A-frame.

4. Install five flange bolts (D) and five flange nuts (D) into the lower portion of the lower roof panel secur-

ing the lower roof panel to the eave angle.

Figure 7-27 Installing the lower roof panels

A

Lower roof panel (CTR-0268)

E

5/16 in. flange nut (S-3611)

D

5/16-18 x 1 flange bolt with sealing washer
(S-10260)

5. After installing the two lower roof panels onto the A-frame rafters, with assistance, position an upper

roof panel (C) onto a A-frame rafter (F).

6. Install a flange bolt (D) and a flange nut (E) to secure the upper roof panel (C) to the rafter (F).

7. With assistance, position another upper roof panel (C) onto the next rafter in the A-frame.

104

Pneg-4078 78 Ft Diameter 40-Series Bin